What Order to Renovate a House: The Right Sequence, Step by Step

The right order to renovate a house is: plan and get permissions, strip out, structural work, roof, windows and external doors, first fix, plastering, second fix, kitchens and bathrooms, decorating, final flooring, then fittings. Anything that goes inside a wall or floor goes in before it is closed up, and anything that can be scratched, stained or knocked goes in last.

Two men seen from behind pointing at a plasterboard wall with filled screw heads

That is the sequence for a full home refurbishment; a single room uses fewer steps in the same order. Most costly mistakes happen at the handovers between stages, when something is measured too early or closed up before anyone has checked it. Rules mentioned below are for England.

What is the right order for a renovation?

  1. Plan, survey and permissions: layout, drawings, notices, lead times
  2. Strip out: only after checking for asbestos
  3. Structural work: beams, new openings, extension, loft, roof structure
  4. Weathertight shell: roof covering, windows and external doors
  5. First fix: electrics, plumbing, heating, ventilation
  6. Insulation and plastering: then time to dry
  7. Floor preparation: levelling, screed, underfloor heating
  8. Second fix joinery: doors, skirting boards, architraves, built-in storage
  9. Kitchens and bathrooms: units, tiling, sanitaryware, glass
  10. Decorating: mist coat, final coats, wallpaper
  11. Final flooring and fittings: floors, light fittings, handles, mirrors, snagging

Where should you start when renovating a house?

Start on paper. Every later trade works from the layout, so fix it first: which walls move, where the kitchen, bathrooms and stairs go, and where each window, door, socket, light and radiator sits. Changing any of that once the walls are boarded means opening them up again.

Windows, doors, glass, worktops and bespoke furniture are made to measure, so ask each supplier for their current lead time while you plan, then order once the opening or space is final.

In England, planning permission, building regulations approval and party wall notices can each have waiting times of their own, so find out what your project needs before you fix a start date, and speak to your council first if your home is listed or in a conservation area.

What happens during strip out and structural work?

Strip-out means removing what is going: old kitchens and bathrooms, plaster, partitions, floors and ceilings. It shows what is behind the surfaces before you commit to the rest of the plan.

Why check for asbestos before the first wall comes down?

HSE says homes built or refurbished before 2000 may contain asbestos in asbestos cement, lagging, insulating board and textured coatings such as Artex. Tell your builder about any asbestos before work starts. Some materials, such as sprayed coatings, lagging and insulating board, should only be removed by an HSE-licensed contractor, and asbestos in good condition is often best left in place (HSE asbestos FAQ).

Structural work follows: beams, moved walls, groundworks, the shell of any extension and the roof structure. If the project goes through building control, ask which inspections it needs and have them done before anything is boarded over.

Should windows go in before or after plastering?

Before. Fit windows and external doors once the structure is finished and the roof is on, so the house is weathertight, new plaster stays dry and the interior trades work in a building that can be locked at night.

Measure for new windows only when the openings are built, because a frame ordered from a drawing may not match what was constructed.

If the house has old sash windows, decide early whether to keep them or replace them, because new sash windows are made to measure; we make them in timber, uPVC and aluminium. For slim frames and glazing bars in an extension, our industrial style windows, in steel or lower-cost steel-look aluminium, follow the same rule: measure once the openings are built. Many people call this slim look "Crittall style". Crittall is a registered trade mark of Crittall Windows Ltd, and No1 London is not affiliated with Crittall Windows Ltd.

Replacement windows in England should meet a minimum energy standard (Approved Document L), and an installer registered with a competent person scheme can certify the work, so ask which scheme and keep the certificate. The rules, plus frame materials and window styles, are covered in the guide to types of windows.

What are first fix and second fix?

First fix is everything hidden once walls, floors and ceilings are closed: cables, pipework, heating, ventilation ducting and stud framing. Second fix is everything fitted onto the finished surfaces: sockets, switches, taps, doors, skirting boards and architraves. Plastering sits between the two.

What goes in at first fix?

Cables and pipes go in now, positioned from the layout you fixed at the start. Photograph every wall and ceiling with the services visible before it is boarded, and ask your builder for a marked-up plan. It saves guesswork when someone drills into a wall years later.

  • Electrics: in England, a new circuit, a replaced consumer unit or changes to circuits around a bath or shower must be certified, usually by an electrician on a competent person scheme, so ask for the certificate (government guidance on electrical safety). No1 London's electricians are NICEIC-approved: see full rewiring.
  • Plumbing and heating: before gas work starts, ask to see the engineer's Gas Safe ID card. The back lists the types of gas work they are qualified to do (HSE). No1 London's engineers are Gas Safe registered: see the plumbing services.

When do plastering and floor preparation happen?

Once first fix has been checked, insulation and plasterboard go in, then plaster. Plaster and screed both add moisture, so agree which goes first. Then leave enough time to dry, following the plasterer's and paint maker's instructions: paint on damp plaster can fail.

What comes first at second fix?

Second fix joinery comes first: internal doors, skirting boards, architraves, stair parts and built-in storage. Kitchens and bathrooms follow, once the walls are finished and the floor is prepared.

Agree with your fitter whether the finished floor goes under the units or up to the plinths, because it changes unit and appliance heights. Have the fitted kitchen designed around the plastered room, not the survey drawing.

In bathrooms, order made-to-measure glass shower screens after the tiling is finished, so the glass fits the finished walls and tray.

When should you decorate and lay final flooring?

Decorate once the trades that drill, cut and fix have finished. A mist coat can go on earlier, but leave the final coats until last: painting and decorating usually goes ceilings first, then walls, then woodwork. Final flooring follows, with the subfloor protected until then. Light fittings, handles, switch plates and mirrors come last, then a snagging walk-round to list every defect and agree dates to fix it.

Bay window opening with the old unit removed, two timber props supporting the roof above and white frames waiting nearby.
Sage green panelled wall with white skirting and sockets, the floor still covered in protective sheeting.

Which sequencing mistakes cause rework?

MistakeWhat goes wrongDo this instead
Boarding over services unseenNo record of where pipes and cables runPhotograph and inspect first
Ordering from drawingsFrames, glass and worktops arrive the wrong sizeMeasure on site once the work is built
Final coats before second fixFresh paint is chipped by drilling and fittingMist coat first, final coats last
Flooring before decoratingDrips, ladders and dust mark the new floorLay floors after decorating
Skipping a party wall noticeNeighbour may seek an injunction (party wall booklet)Check first whether you need one

Does the renovation order change for an extension, a loft or one room?

The relative order stays the same. What changes is what sits at the front.

  • Extension: groundworks, structure and roof come first, then windows and doors, then first fix.
  • Loft conversion: steelwork, roof alterations and rooflights come first, then the new stair, whose position is fixed early because it takes space from the floor below. Details are on the loft conversions page.
  • Single room: skip the structure and shell stages unless walls or windows are moving, then follow the same run from strip-out to final flooring.

What should you ask your builder before work starts?

  • Programme: which trade is on site when, and which decisions you must make by when.
  • Paperwork: who notifies building control, who serves any party wall notices and who supplies the certificates.
  • Measurements: what is made to measure, and when it will be surveyed.
  • Living arrangements: whether you can stay at home.

Frequently Asked Questions

Can you live in the house while it is being renovated?

Usually not during strip-out, structural work and first fix, because the kitchen and bathroom are often out of use and power and water are switched off for periods. Working floor by floor can let you stay, but it usually lengthens the programme, so decide before it is agreed.

Should the kitchen or the bathroom come first?

Both follow plastering and floor preparation, so the real question is which room you can least do without. If the house has one bathroom and you are living there, finish it first: a temporary kitchen with a kettle and microwave is easier to live with than no bathroom.

Do building regulations affect the order of work?

Yes. In England, some work cannot start until building control has been told (Building Regulations 2010, regulation 16), while work by a registered installer, such as replacement windows, is certified afterwards.

Sources

Final Thoughts

Hidden work first, visible work last, and nothing made to measure until the measurements are real: keep to that and you are unlikely to be opening up finished work.

When the openings are built, ask for a free estimate on new sash windows or industrial style windows, or compare samples and finishes at our showroom in Fulham.

Ready to Transform Your Home?

Get A Free Quote

Written by No1 LondonPublished 15 July 2026 · Updated 13 November 2026

Building & Construction

About the author

No1 London

Windows, doors and bespoke furniture in London

No1 London brings windows, doors, glass, bespoke kitchens and furniture together under one brand and one roof, for homes across London and Surrey.

Our showroom at 9 Royal Parade, Dawes Road, Fulham, SW6 7RE has samples of doors, windows, glass, stone and finishes. It is open Monday to Friday, 9am to 5pm, walk-ins are welcome and you can book a free consultation.

More articles by No1 London

Get in touch Get Your Free Estimate.

Loading the map may set cookies from Google.

Book a showroom visit Call us now